Weekly Project Updates 11/17/25 - 11/21/25
Hello Stakeholders!
Here are project updates for the week of November 17th-21st:
- The concrete crew completed all concrete work on 9th Street and portions of Franklin Avenue ahead of the base crew’s arrival.
- The base crew has been preparing Franklin Avenue for the first (bottom) lift of asphalt to help seal the roadway before colder weather sets in.
- The pipe crew continued installing the main storm line along 10th Street west of Franklin and began installing inlets on Franklin Avenue north of 10th Street.
- Weather permitting, the paving crew is expected to begin paving the bottom lift of asphalt on Franklin Avenue next week.
- The pipe crew will complete inlet installation on Franklin north of 10th Street, then shift to installing the main line east on 10th Street toward Roosevelt Avenue.
- The concrete crew will continue replacing curb and gutter sections and completing concrete work around newly installed inlets.
Weather permitting, work activities are Monday - Friday, 7:00 am - 5:00 pm.

Share Weekly Project Updates 11/17/25 - 11/21/25 on Facebook
Share Weekly Project Updates 11/17/25 - 11/21/25 on Twitter
Share Weekly Project Updates 11/17/25 - 11/21/25 on Linkedin
Email Weekly Project Updates 11/17/25 - 11/21/25 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends