Weekly Project Updates 11/10/25 - 11/14/25

Hello Stakeholders!

Here are project updates for the week of November 10th-14th:

  • The pipe crew was off-site Wednesday and Thursday assisting the Water Department with a water main break. They returned Friday, 11/7, to remove the temporary water line and clean up Franklin Avenue between 9th and 10th Streets.
  • We are awaiting the landscaping contractor to begin restoring the areas marked for completion.
  • The concrete crew will return to replace sections of concrete on 9th Street and Franklin Avenue, and possibly on 10th Street once enough areas are ready for replacement.
  • With Veterans Day on Tuesday and our offices closed in observance, we extend our sincere thanks to all veterans and their families for their service. Our contractor and crews may continue working that day at their discretion.
  • The pipe crew will continue installing storm pipe along 10th Street west of Franklin Avenue toward Colorado Avenue.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.