Weekly Project Updates 10/27/25 - 10/31/25

Here are project updates for the week of October 27th-31st:

  • Crews successfully installed the 42-inch stormwater pipe and protected the nearby waterline that was exposed along the trench. Both tasks were completed with great care and precision.
  • Concrete work on 9th Street was delayed to allow the new pavement additional time to cure and harden before crews return.
  • The landscaping crew will be on site Friday, October 24th, and throughout the week of October 27th to clean up and restore the few remaining yards affected by construction.
  • The tree contractor will mobilize late next week to trim trees that were damaged during pipe installation. They will also trim ahead of the pipe crew along 10th Street to prepare for upcoming work.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.