Project weekly update for 6/5/23 - 6/9/23
CLOSED: This discussion has concluded.
The Garfield Harrison Storm Drain Project work activities for this coming week (6/5-6/9) include:
- Storm sewer and waterline crews are continuing to work on 4th Street and making good progress.
- Concrete curb, gutter, and sidewalk repairs are ongoing through next week.
- Bottom mat paving is to occur today or possibly Monday depending on weather at 4th Street & Sheridan Avenue.
Weather permitting, work activities are Monday-Friday, 7am to 5pm.
Share Project weekly update for 6/5/23 - 6/9/23 on Facebook
Share Project weekly update for 6/5/23 - 6/9/23 on Twitter
Share Project weekly update for 6/5/23 - 6/9/23 on Linkedin
Email Project weekly update for 6/5/23 - 6/9/23 link
![<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>](http://d2gu4vothxmtom.cloudfront.net/assets/ajax-loader-transparent-aebc793d0064383ee6b1625bf3bb32532ec30a5c12bf9117066107d412119123.gif)
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends