Weekly Project Updates 8/4/25 - 8/8/25
Hello Stakeholders!
Here are the project updates for the week:
- Paving of the top lift on Colorado Avenue from 7th Street to Birkley Court and bottom lift on Franklin Avenue is complete.
- Crews will continue to pour concrete on inlets, sidewalks, curb and gutter on Franklin and Sheridan Avenues.
- Crews will continue to install pipe on 8th Street west of Colorado Avenue, backfilling and compacting as they go.
- Inlets on 8th Street, west of Colorado will be installed.
- Crews will finish paving around Garfield Elementary School prior to the first day of school.
Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.