Project weekly update 8/14/23 - 8/18/23

The Garfield Harrison Storm Drain Project work activities for this coming week (8/14-8/18) include:

  1. Concrete replacements are still ongoing for a couple more weeks; however, pipe installation is largely complete for this year.
  2. Bottom and top mat paving will be ongoing for the next couple weeks also.
  3. The end of this month will include punch-list items and then the Garfield Harrison Project will be back for Phase 3 next spring.

Weather permitting, work activities are Monday-Friday, 7 a.m. to 5 p.m.

Share on Facebook Share on Twitter Share on Linkedin Email this link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>