Project Weekly Update 5/5/25 - 5/9/25

Hello Stakeholders!

Here are the project updates for this week (5/5-5/9):

1. Connell utility installation crews are not active on site for the next couple weeks and 8th Street continues to be fully open to traffic.
2. Hoff is working on concrete repairs on Roosevelt, near 9th Street.
3. Crews are preparing Roosevelt north of 8th Street for paving.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.