Project Weekly Update 4/28/25 - 5/2/25

Hello Stakeholders!

Here are the project updates for this week (4/28-5/2).

  1. Now that 8th Street has been re-opened, the project will be scaling back and there will be limited activities for a couple weeks.
  2. Concrete work will still be on-going, and sidewalks and curb & gutter installations will continue through the first half of the week.
  3. Street preparation for paving will be on-going at Roosevelt and 9th Street in anticipation of paving in May.

Weather permitting, work activities are Monday – Friday, 7:00 am – 5:00 pm.