Project Updates for 4/6/26 - 4/10/26
Below are project updates from this week, as well as for the upcoming week (April 6th-10th):
- Crews began work on West 10th Street, west of Colorado Avenue and installed the first inlet and connecting pipe to the existing main.
- A second crew is completing cleanup and backfilling along the new curb and gutter in the eastern portion of the project near Roosevelt Avenue and 11th Street.
- Beginning the week of 4/6, paving crews will return to mill and profile 10th Street, Roosevelt Avenue, and 11th Street, and begin reconstruction of larger sections at the 11th Street and Roosevelt Avenue intersection.
- The pipe crew will continue installing inlets and storm pipe along West 10th Street between Colorado Avenue and Douglas Avenue. Advance signage has been installed for the upcoming closure of the Colorado Avenue and 10th Street intersection. This closure is scheduled to begin April 13th and last approximately three weeks.
Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Share Project Updates for 4/6/26 - 4/10/26 on Facebook
Share Project Updates for 4/6/26 - 4/10/26 on Twitter
Share Project Updates for 4/6/26 - 4/10/26 on Linkedin
Email Project Updates for 4/6/26 - 4/10/26 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends