Project Updates for 3/30/26 - 4/3/26

Below are project updates from this week, as well as for the upcoming week (March 30th - April 3rd):

  • The pipe crew completed the final tie-in from the inlet on 11th Street west of Roosevelt Avenue and will move to the West 10th Street segment, west of Colorado Avenue, the week of 3/30.
  • The base and paving crews completed the remaining sections of 10th Street as well as areas on Roosevelt Avenue and a portion of 11th Street, east of Roosevelt Avenue.
  • The concrete crew completed the remaining inlets, curb, gutter, and sidewalks on 10th Street, including installation of an ADA ramp at the northwest corner of 10th Street and Roosevelt Avenue.
  • The pipe crew will begin operations along West 10th Street (west of Colorado Avenue), saw cutting and potholing to verify utility locations and potential underground conflicts. The section, between Colorado and Douglas Avenues will be closed to through traffic but remain open to local residents.
  • The concrete crew will complete the final inlet on the east side of the project at 11th Street and Roosevelt Avenue.

Weather permitting, work activities are Monday - Friday, 7:00 am-5:00 pm.

Pictures of inlet installation and street paving.