Project updates 6/1/26 - 6/5/26

Hello Stakeholders,
Below are project updates from this week and the upcoming week (6/1/26 - 6/5/26):
- Concrete repairs were completed on Roosevelt and 11th Street and on the south side of West 10th Street from Colorado to Douglas.
- Subgrade prep work is underway at the Colorado and 10th Street intersection prior to paving, along with prepping 10th Street east of Colorado.
- Paving crew raised two manholes that were buried (one on 8th Street and the other on Colorado and 4th Street).
- Paving crew paved Colorado and 10th Street intersection and put a bottom lift and leveling coarse on the 10th Street section east of Colorado. They will also pour concrete on mailbox pads on the west section of 10th Street.
- Survey was completed on both sides of west 10th Street to help finalize work needed along the west 10th Street section.
- Landscaping crew will return to complete work on 11th Street and also prep for west 10th Street.
Image Caption
Important Notice:
Upcoming Temporary Closure at 8th Street and Colorado Avenue Intersection
City crews will repair a leaking water valve at the intersection of west 8th Street and Colorado Avenue starting next week. Because the damaged valve is in the middle of the intersection, the intersection will be closed during repairs from Tuesday through Thursday, weather permitting. Residents should expect delays and should detour to Taft or Garfield Avenues.
Starting Tuesday, crews will dig around the 12-inch water main to prepare for a new valve installation. On Wednesday, the Utilities contractor will install a temporary valve to help keep water service running for nearby customers during the repair work. For questions about the repair or water services, contact the Utilities Department at 970-962-3000.
Thank you for your contribution!