Construction Update: Jan 12-16

Hello Loveland!

Here are our project updates and a look at upcoming work.

Progress Jan. 12-16

  • Crews backfilled and completed asphalt patches at both locations where line stops were removed along 29th Street.
  • Another crew installed 16-inch water line from 28th Street south to Lake Drive, then east across N. Taft Avenue within Lake Drive. This will connect to the existing water line near the Thompson Ambulance facility after disinfection and pressure testing.
  • Crews installed 2-inch and 3-inch temporary water service lines throughout Connecticut Place cul-de-sac and homes adjacent to N. Taft Avenue up to 20th Street.
    • Reminder: If placed on temporary water, you will not be charged for water usage; leave a tap open to prevent freezing of more vulnerable temporary lines. Frozen lines delay progress and can affect water service.


Week of Jan. 12: 8” PVC waterline construction in the intersection of N. Taft Avenue and 28th Street



Week of Jan. 12: 8” PVC waterline to tie-into Lake Drive



Jan 10: 29th Street line stop removal



Jan 15: Drone picture from above 29th Street shows paving progress and near completion along 29th Street


Upcoming work Jan. 19-23

  • Expect brief lane shifts on 29th Street on Wednesday for installation of a new fire hydrant and water service to the Thompson Rehabilitation Center.
  • Begin constructing the 16-inch water line north along N. Taft Avenue from 20th Street.

Looking forward

  • Heavy construction will focus on 18th–22nd and 25th–29th streets as crews install new 16-inch pipeline.
  • Current detours will remain in place.

Working hours

Weather permitting, work activities are Monday – Friday, 7:00 a.m. – 5:00 p.m. with occasional Saturday work needed.

To contact the project team, call 970-962-3521 or email UtilitiesInfo@cityofloveland.org.

Thank you for your patience as we complete these improvements.