Weekly update 11/2/26 - 11/8/26
Hello Stakeholders!
Here are the project updates for the week of 11/2/26-11/8/26:
The project is scheduled to be completed with streets open to traffic by Friday, November 6, 2026!
- Block 5 (Garfield to Railroad Ave.)
- Vehicle access will be limited to Garfield Ave. only.
- Burlington Northern Santa Fe (BNSF) railroad crossing & 4th Street
- Access across the BNSF railroad tracks is fully closed to vehicles
- Pedestrian crossings at the tracks are shifting; please follow posted signage.
- Concrete sealing, signing, and striping.
- Block 4 (Cleveland to Railroad Ave.)
- The block is open to traffic with limited southbound access at Railroad Ave. (east).
- Blocks 1, 2, 3, 4 and 5
- Permanent sculptures will be installed, which may require the temporary closure of parking spots to accommodate equipment.
- Block 3 (Lincoln to Cleveland) (non-project related work)
- Sidewalk closure at 225 E. 4th Street; please follow posted signage.
- Painter’s Alley (non-project related work)
- Five of the eight conduits serving businesses on the north end of the alley have been installed.
- The new 5’x3’ vault on the north end has been installed.
- Electricians have begun mounting metering gear in preparation for switching services to underground.
- City of Loveland crews have started removing transformers from services already converted to underground.
- Next week, crews will begin coordinating with customers on the north side of the alley to convert their services to underground.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly update 11/2/26 - 11/8/26 on Facebook
Share Weekly update 11/2/26 - 11/8/26 on X (formerly Twitter)
Share Weekly update 11/2/26 - 11/8/26 on Linkedin
Email Weekly update 11/2/26 - 11/8/26 link