Weekly update 10/26/26 - 11/1/26
Hello Stakeholders!
Here are the project updates for the week of 10/26/26-11/1/26:
- Block 5 (Garfield to Railroad Ave.)
- Vehicle access will be limited to Garfield Ave. only.
- Burlington Northern Santa Fe (BNSF) railroad crossing & 4th Street
- Access across the BNSF railroad tracks is fully closed to vehicles
- Pedestrian crossings at the tracks are shifting; please follow posted signage.
- Installed concrete paving, sidewalk pavers, and boulder seat walls.
- Block 4 (Cleveland to Railroad Ave.)
- The block is open to traffic with limited southbound access at Railroad Ave. (east).
- Installed concrete paving (intersection) and electric work.
- Blocks 1, 2, 3 and 5
- Permanent sculptures will be installed, which may require the temporary closure of parking spots to accommodate equipment.
- Block 3 (Lincoln to Cleveland) (non-project related work)
- Sidewalk closure at 225 E. 4th Street; please follow posted signage.
- Painter’s Alley (non-project related work)
- East side of the alley has been completed.
- The new 5'x3' vault on the north side of the alley, along with the conduits routed from the 7'x14' vault, will be flow‑filled.
- New conduits will be installed to serve 120 E 4th St, 118 E 4th St, 116 E 4th St, 112 E 4th St, and 104 E 4th St.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly update 10/26/26 - 11/1/26 on Facebook
Share Weekly update 10/26/26 - 11/1/26 on X (formerly Twitter)
Share Weekly update 10/26/26 - 11/1/26 on Linkedin
Email Weekly update 10/26/26 - 11/1/26 link