Weekly project updates 9/29/25 - 10/3/25

Hello, Loveland!

Here are the project updates for next week (9/29/25-10/5/25):

  • Crews will complete asphalt patching at the new Lincoln and east 3rd Street crosswalks this week.
    • Once complete, both northbound lanes on Lincoln and access at east 3rd Street will be restored.
  • Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenues) are fully closed to motorists. All businesses remain open and accessible to people walking.
  • Implementation of “Construction Workzone Phase 1B” has started on Blocks 1 and 2.
    • During this phase, pedestrian access will shift to the center of the roadway, where new pavement will connect to temporary ramps leading to each business. All businesses will remain open.


Crews have completed the Lincoln Avenue and 4th Street stormwater improvements; however, alternating single lanes on Lincoln Avenue remain in effect while the project completes 3rd Street crosswalk installations. The map shows available parking in downtown Loveland while Blocks 1, 2 and 5 are under construction. For parking, visitors may also visit lovgov.org/DowntownParking.

Weather permitting, work activities are Monday-Saturday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link) or 970-962-2524.


Thank you for your continued support as we revitalize 4th Street!