Here are the project updates for next week (6/23/25-6/27/25):
- Blocks 1 and 2 (Washington to Lincoln) and Block 5 (Garfield to RR Ave.) are fully closed to motorists.
- Storm sewer installations on Block 1 & 2 will be completed this week.
- Conduit installation has started.
- Crews are installing stormsewer, waterlines, water services, meters, and fire lines in Block 5.
- Crews will replace water valves in Railroad Avenue (east) next week. Please see map of work limits. Both Railroad Avenues are anticipated to be open Friday, June 27.
- The Garfield & 4th Street intersection is anticipated to be open by July 3, 2025.
- Crews will be potholing on the east side of Lincoln Avenue between Sweetheart Alley and 4th Street. This work will impact the east sidewalks and parallel parking spots on the east side of the roadway.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 6/23/2025 - 06/27/2025 on Facebook
Share Weekly project updates 6/23/2025 - 06/27/2025 on Twitter
Share Weekly project updates 6/23/2025 - 06/27/2025 on Linkedin
Email Weekly project updates 6/23/2025 - 06/27/2025 link