Weekly project updates 12/15/25 - 12/19/25

Hello, Loveland!

Here are the project updates for next week (12/22/25-12/28/25).

  • No work will occur on 12/25/25 and 12/26/25.
  • Block 3 (Lincoln to Cleveland Avenues)
    • The block is closed to vehicular traffic but remains open to pedestrians.
    • Crews are installing the 12” watermain.
  • Block 5 (Garfield to Railroad Avenues)
    • This block is closed to vehicular traffic but remains open to pedestrians.
    • The Garfield and west 4th Street intersection will reopen to northbound, southbound and westbound traffic by the end of the day Wednesday, 12/24/25.
    • Concrete paving will begin this week.
    • Xcel will be potholing on the east Railroad Avenue for an unrelated project.

Weather permitting, work activities are Monday-Saturday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued support as we revitalize 4th Street!