Weekly project updates 12/1/25 - 12/7/25
Hey, Loveland
Here are the project updates for this week (12/1/25-12/7/25).
- Block 5 (Garfield to Railroad Aveenues) boulder seat walls, irrigation sleeves, light pole foundations and concrete work.
- Block 3 (Lincoln to Cleveland Avenues) construction begins Monday, December 1, 2025.
- The block will be closed to vehicular traffic from the west side of Cleveland Avenue to the east side of Lincoln Avenue.
- Pedestrian access will be maintained with fencing to ensure access to businesses.
Weather permitting, work activities are Monday-Saturday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!