Weekly project updates 10/6/25 - 10/12/25

Hello Loveland,

Here are the project updates for next week (10/6/25-10/12/25).

  • Both lanes of Lincoln Avenue are open!
  • Blocks 1 and 2 (Washington to Lincoln) and Block 5 (Garfield to Railroad Avenue) are fully closed to motorists.
    • Implementation of “Construction Workzone Phase 1B” has started on Blocks 1 and 2.
    • During this phase, pedestrian access will shift to the center of the roadway, where new pavement will connect to temporary ramps leading to each business. All businesses will remain open.
  • Building headers are being installed on Block 1 and Block 2.


An aerial of Blocks 1 and 2 facing west. Pictured is the completion of concrete paving on Block 1 (between Washington Avenue and Jefferson Avenue), as well as Block 2 (Jefferson Avenue to Lincoln Avenue). Pedestrian fencing is placed in the middle of Block 1 to guide pedestrians to their destinations while new sidewalk is installed on Block 1.

Weather permitting, work activities are Monday-Saturday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued support as we revitalize 4th Street!