Weekly project updates 10/13/25 - 10/18/25
Hello, Loveland!
Here are the project updates for next week (10/13/25-10/18/25):
- Crews will perform final asphalt patching and striping at Washington Avenue and east 4th Street this week.
- Work will include closure of the southbound lane from Monday, October 13, 2025, through Friday, October 17, 2025.
- Southbound traffic will be detoured to east 5th Street, Cleveland Avenue and east 1st Street.
- Blocks 1 and 2 (Washington to Lincoln Avenues) and Block 5 (Garfield to Railroad Avenues) are fully closed to motorists.
- Implementation of “Construction Workzone Phase 1B” is in full effect on Blocks 1 and 2.
- During this phase, pedestrian access will shift to the center of the roadway, where new pavement will connect to temporary ramps leading to each business. All businesses will remain open.
- Crews are installing the concrete paver base on Blocks 1 and 2 and installing landscape items and grading on Block 5 this week.
Updated map as of Oct. 10, 2025 to illustrate a temporary closure at Washington Avenue and east 4th Street from 10/13/2025 - 10/17/2025 to complete asphalt patching and striping.
Using recycled barrels and cones from Loveland Barricade, Detour Darrin was created to help guide pedestrians through Blocks 1 and 2 while new sidewalks are installed. Detour Darrin is a hero and champion for pedestrian access and safety. Weather permitting, work activities are Monday-Saturday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 10/13/25 - 10/18/25 on Facebook
Share Weekly project updates 10/13/25 - 10/18/25 on Twitter
Share Weekly project updates 10/13/25 - 10/18/25 on Linkedin
Email Weekly project updates 10/13/25 - 10/18/25 link