Weekly project updates 1/19/26 - 1/25/26
Hello, Loveland!
Here are the project updates for this week (1/12/26-1/18/26).
- City offices are closed Monday, Jan.19, but crews will be working.
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicles; sidewalks are open for business access.
- Replacement of fire hydrants, meters and fire lines continues.
- Block 5 (Garfield to Railroad Avenue)
- Block remains closed to vehicles; sidewalks are open for business access.
- Crews are installing streetlights and seat walls.
- Building header installation and sidewalk replacements are underway.
Weather permitting, work activities are Monday-Saturday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project updates 1/19/26 - 1/25/26 on Facebook
Share Weekly project updates 1/19/26 - 1/25/26 on Twitter
Share Weekly project updates 1/19/26 - 1/25/26 on Linkedin
Email Weekly project updates 1/19/26 - 1/25/26 link