Here are the project updates for the week of 9/21/26-9/27/26:
- Block 5 (Garfield to Railroad Ave.)
- Vehicle access will be limited to Garfield Ave. only.
- Vehicle access will be limited to Garfield Ave. only.
- Burlington Northern Santa Fe (BNSF) railroad crossing at 4th Street
- Access across the BNSF railroad tracks is FULLY CLOSED at 4th Street.
- All foot traffic will need to cross the tracks at a legal crossing located at 1st Street or 6th Street.
- Block 4 (Cleveland to Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Concrete work, boulder seat walls, and concrete pavers.
- Blocks 1, 2, 3 and 5
- Permanent sculptures will be installed, which may require the temporary closure of parking spots to accommodate equipment.
- Garfield Ave. (1st to 7th Street) (non-project related work)
- Asphalt paving
- Expect on-street parking closures and lane shifts.
- Block 3 (Lincoln to Cleveland Ave.) (non-project related work)
- Westbound 4th closed to vehicles for steel beam installation at 209 E. 4th Street/Sky Bear Brewery and Pub and building demolition work at 225 E. 4th Street/The Rio Grande Mexican Restaurant.
- Expect sidewalk closures directly in front of buildings, please follow posted signage.
- Sweetheart Alley (Lincoln to Cleveland Ave.) (non-project related work)
- West half of alley closed from Cleveland to 225 E. 4th Street for building demolition and asbestos remediation work.
- West half of alley closed from Cleveland to 225 E. 4th Street for building demolition and asbestos remediation work.
- Painter’s Alley (non-project related work)
- Beginning 9/21, City of Loveland Utilities will excavate an area behind the Love Shack at 120 E 4th St at the alley T to install a new 5x8 underground electric power vault.
- The vault will feed one or more new transformers, to be installed the week of 9/21 or 9/28, weather permitting.
- The new transformers are due to be energized the week of October 5.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly project update 9/21/26 - 9/27/26 on Facebook
Share Weekly project update 9/21/26 - 9/27/26 on X (formerly Twitter)
Share Weekly project update 9/21/26 - 9/27/26 on Linkedin
Email Weekly project update 9/21/26 - 9/27/26 link