Weekly project update 8/17/26 - 8/23/26

Hello Stakeholders!

Here are the project updates for the week of 8/17/26-8/23/26:

  • Block 5 (Garfield to Railroad Ave.)
    • Vehicle access will be limited to Garfield Ave. only.
  • Burlington Northern Santa Fe (BNSF) Railroad crossing & 4th Street
    • Access across the BNSF railroad tracks is fully closed to vehicles.
    • South parking lot accesses and pedestrian crossings at the tracks will shift; please follow posted signage.
  • Block 3 (Lincoln Ave. to Cleveland Ave)
    • Protective scaffolding will be erected in front of 209 E. 4th St. at Sky Bear Brewery and Pub on Monday, 8/17 in preparation for demolition work.
    • Two adjacent parallel parking spots will be closed during construction (8/17-9/1).
  • Block 4 (Cleveland to Railroad Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Sidewalk replacement work continues. Please expect crews working as early as 5 a.m. to accommodate business hours.
    • Concrete work, fiber optic relocations and power infrastructure are underway.
  • Cleveland Ave.
    • West on-street parking closures between E. 6th Street and Backstage Alley
    • West lane closure at E. 4th Street: 8:30 a.m. – 3:30 p.m.
  • Garfield Ave. (1st to 7thStreet) (non-project related work)
    • Concrete curb, gutter and sidewalk replacements.
    • Expect on-street parking closures and lane shifts.

Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued patience and support.