Weekly project update 7/6/26 - 7/10/26
Dear Stakeholders,
Project updates for 4th Street during the week 7/6/26-7/10/26 are as follows:
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Landscape irrigation and planting.
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Concrete pavement.
- Concrete curbs at the corner of Aims Community College.
- Roadway grading at various corners of the N. Railroad Avenue intersection.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.