  • Block 3 (Lincoln to Cleveland Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Final inspections, punch list items and miscellaneous clean-up.
    • Block is scheduled to open on Friday, July 24th!
  • Block 4 (Cleveland to N. Railroad Ave.)
    • Block remains closed to vehicle traffic; businesses are open to pedestrian access.
    • Concrete work and power infrastructure in the N. Railroad Ave. intersection.
    • Old roadway and sidewalk removals beginning on the East side of the Burlington Northern Santa Fe (BNSF) railroad tracks.
    • South 4th Street parking lot egress improvements.

Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.

Thank you for your continued patience and support.

Share Weekly project update 7/20/26 - 7/26/26 on Facebook Share Weekly project update 7/20/26 - 7/26/26 on X (formerly Twitter) Share Weekly project update 7/20/26 - 7/26/26 on Linkedin Email Weekly project update 7/20/26 - 7/26/26 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>