Weekly project update 7/20/26 - 7/26/26
Hello Loveland!
Here are the project updates for the week of 7/20/26-7/26/26.
- Block 3 (Lincoln to Cleveland Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Final inspections, punch list items and miscellaneous clean-up.
- Block is scheduled to open on Friday, July 24th!
- Block 4 (Cleveland to N. Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Concrete work and power infrastructure in the N. Railroad Ave. intersection.
- Old roadway and sidewalk removals beginning on the East side of the Burlington Northern Santa Fe (BNSF) railroad tracks.
- South 4th Street parking lot egress improvements.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly project update 7/20/26 - 7/26/26 on Facebook
Share Weekly project update 7/20/26 - 7/26/26 on X (formerly Twitter)
Share Weekly project update 7/20/26 - 7/26/26 on Linkedin
Email Weekly project update 7/20/26 - 7/26/26 link