Weekly project update 4/20/26 - 4/26/26
Hello Stakeholders!
Here are the project updates for this week (4/20/26-4/26/26).
- Cleveland Avenue
- Parking closures and alternating lane sifts for striping activities.
- Major work on Cleveland will be completed this week!
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Boulder seatwalls, concrete and electric work.
- Block 4 (Cleveland to north Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Storm sewer and power conduit installations.
- North Railroad Avenue (east)
- Intersection is closed
- Utility installation
- Block 5 (Railroad Avenue (west) to Garfield Avenue.)
- Block will be closed to vehicles for approximately four days for landscaping installations. Sidewalks will remain open.
Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HIPStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project update 4/20/26 - 4/26/26 on Facebook
Share Weekly project update 4/20/26 - 4/26/26 on Twitter
Share Weekly project update 4/20/26 - 4/26/26 on Linkedin
Email Weekly project update 4/20/26 - 4/26/26 link