Weekly project update 4/13/26 - 4/19/26
Hello, Loveland!
Here are the project updates for this week (4/13/26-4/19/26).
- Cleveland Avenue
- Southbound Cleveland Avenue will remain in a single-lane configuration.
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Boulder seatwall, concrete and electric work.
- Non-project related façade work (209 E. 4th Street). Sidewalk impacts.
- Block 4 (Cleveland to N. Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open to pedestrian access.
- Fireline installations.
- Storm sewer installations.
- Block 5 (Railroad Avenue west to Garfield Avenue)
- Landscaping installations.
- N. Railroad Avenue (east)
- Intersection closure (Area 1 below).
- Utility installations.
- Painters Alley (non-project related)
- Vault installation, Loveland Utilities.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HIPStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project update 4/13/26 - 4/19/26 on Facebook
Share Weekly project update 4/13/26 - 4/19/26 on Twitter
Share Weekly project update 4/13/26 - 4/19/26 on Linkedin
Email Weekly project update 4/13/26 - 4/19/26 link