Weekly project update 3/9/26 - 3/15/26
Hello, Loveland!
Here are the project updates for this week (3/9/26-3/15/26).
Please note additional non-project related work at 3rd Street and Cleveland Avenue.
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open for business access.
- Streetlight bases, unground power work, concrete roadside bollard bands and roadway grading.
- Block 4 (Cleveland to North Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open for business access.
- Waterline, water services and fireline installations.
- Block 5 (Garfield to Railroad Avenue)
- Block nearing completion!
- Sidewalk completion and punch list reviews.
- 3rd Street and Painter’s Alley
- Traffic will only be allowed to travel westbound at 3rd Street and Cleveland Avenue.
- Power, waterline and concrete sidewalk improvements.
Starting on Monday, March 9, at 3rd Street and Cleveland Avenue eastbound travel will not be accessible to traffic for sidewalk bulb outs on the corners. Delays should be expected within this area. Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project update 3/9/26 - 3/15/26 on Facebook
Share Weekly project update 3/9/26 - 3/15/26 on Twitter
Share Weekly project update 3/9/26 - 3/15/26 on Linkedin
Email Weekly project update 3/9/26 - 3/15/26 link