Weekly project update 2/9/26 - 2/15/26
Hello, Loveland!
Here are the project updates for this week (2/9/26-2/15/26).
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open for business access.
- Stormwater improvements, electric conduits and boulder art pedestal installations.
- Lane shifts and on-street parking closures on Cleveland Avenue (6th to 3rd Street). Please expect delays in this area.
- Block 5 (Garfield to Railroad Avenue)
- Block remains closed to vehicles; pedestrian access provided via the roadway and temporary access bridges.
- Crews are installing concrete underlayment for pavers and building headers.
- Concrete paver installations start this week.
- BNSF Railroad Avenue – Waterline Casing
- Crews will install a waterline casing beneath the BNSF railroad.
- This phase of work will require closure of:
- Railroad Avenue (east) from 4th Street north to the alley.
- 4th Street westbound between the two Railroad Avenue intersections.
- Please see map below.

Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project update 2/9/26 - 2/15/26 on Facebook
Share Weekly project update 2/9/26 - 2/15/26 on Twitter
Share Weekly project update 2/9/26 - 2/15/26 on Linkedin
Email Weekly project update 2/9/26 - 2/15/26 link