Weekly project update 2/23/26 - 3/1/26
Hello, Loveland!
Here are the project updates for this week (2/23/26-3/1/26):
Please see map below for work area limits and access.
- Block 3 (Lincoln to Cleveland Avenue)
- Block remains closed to vehicle traffic; sidewalks are open for business access.
- Crews work to begin electric conduits, streetlight foundations, boulder art pedestal/seat wall installations and roadway grading.
- Lane shifts and on-street parking closures on Cleveland Ave (6th to 3rd Street). Please expect delays in this area.
- Block 4 (Cleveland to N. Railroad Avenue)
- Block remains closed to vehicle traffic; sidewalks are open for business access.
- Demolition activities
- Waterline work starts
- BNSF Railroad – Waterline Casing
- Auger work and casing is complete and is ahead of schedule!
- Waterline tie-ins east and west of the casing.
- Learn more about this process by watching our video here: https://youtu.be/XByLOaDqHBM?si=4KxANEVzzrwAZ_Ek
- Block 5 (Garfield to Railroad Avenue)
- Block remains closed to vehicles; pedestrian access provided via the roadway and temporary access bridges.
- Concrete paver sidewalk installations continue.
Starting on Monday, Feb.16, we will close Block 4 to begin our next phase of work. The map above shows the lane shifts and street closures. Weather permitting, work activities are Monday-Friday, 7:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org(External link) or 970-962-2524.
Thank you for your continued support as we revitalize 4th Street!
Share Weekly project update 2/23/26 - 3/1/26 on Facebook
Share Weekly project update 2/23/26 - 3/1/26 on Twitter
Share Weekly project update 2/23/26 - 3/1/26 on Linkedin
Email Weekly project update 2/23/26 - 3/1/26 link