Weekly project update 10/5/26 - 10/11/26
Hello Stakeholders!
Here are the project updates for the week of 10/5/26-10/11/26:
- Block 5 (Garfield to Railroad Ave.)
- Vehicle access will be limited to Garfield Ave. only.
- Concrete sealing at 4th & Garfield intersection. Lane shifts with flagging operations.
- Burlington Northern Santa Fe (BNSF) Railroad crossing & 4th Street
- Access across the BNSF railroad tracks is fully closed to vehicles.
- Pedestrian crossings at the tracks are shifting; please follow posted signage.
- Concrete work, pavers and landscaping.
- Block 4 (Cleveland to Railroad Ave.)
- Block remains closed to vehicle traffic; businesses are open to pedestrian access.
- Concrete work, signing/striping, and landscaping.
- Blocks 1, 2, 3 and 5
- Permanent sculptures will be installed, which may require the temporary closure of parking spots to accommodate equipment.
- Block 3 (Lincoln to Cleveland) (non-project related work)
- Sidewalk closure at 225 E. 4th Street; please follow posted signage.
- Painter’s Alley (non-project related work)
- East side of alley will be closed
- Conduit trenching will begin behind 120 E 4th St, heading east, and will continue through to 325 N Cleveland Ave.
- A 5’×3’ vault will be installed approximately 20 feet west of 325 N Cleveland Ave
- New conduit installation will be performed by trenching from the 5’ × 3’ vault to the existing meter gear serving the business.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly project update 10/5/26 - 10/11/26 on Facebook
Share Weekly project update 10/5/26 - 10/11/26 on X (formerly Twitter)
Share Weekly project update 10/5/26 - 10/11/26 on Linkedin
Email Weekly project update 10/5/26 - 10/11/26 link