- Block 5 (Garfield to Railroad Ave.)
- Vehicle access will be limited to Garfield Ave. only.
- Burlington Northern Santa Fe (BNSF) railroad crossing & 4th Street
- Access across the BNSF railroad tracks is fully closed to vehicles.
- Pedestrian crossings at the tracks are shifting; please follow posted signage.
- Crews will be paving at the Railroad Avenue (west) intersection and adjacent west parking lots. Please follow posted signage.
- Block 4 (Cleveland to Railroad Ave.)
- Open to traffic with limited southbound access at Railroad Ave. (east)
- Vehicle access will be limited to Cleveland Ave. (only) on Wednesday, October 21st (weather dependent) for striping on Railroad Ave. (east) between E. 3rd and E. 4th
- Stone Mountain/Aims parking lot will be fully closed Wednesday, October 21st for parking lot maintenance
- Blocks 1, 2, 3 and 5
- Permanent sculptures will be installed, which may require the temporary closure of parking spots to accommodate equipment.
- Block 3 (Lincoln to Cleveland) (non-project related work)
- Sidewalk closure at 225 E. 4th Street; please follow posted signage.
- Painter’s Alley (non-project related work)
- The alley will remain closed in both directions. Trenching on the east side will be completed. Flow fill will be poured over all open trenches; through‑traffic will remain closed, but approximately 75% of the alley will be open for access.
- One new 5’x3’ vault will be installed. Crews will trench the north side of the alley and install conduit from the 7’×14’ vault to a new 5’×3’ vault. Service conduits will be bored to the individual meters behind each business.
- The first "cutover," or switch from the old to the new power source, is scheduled for Friday. The building at 140 E 4th St will be fed power from the new transformers.
Weather permitting, work activities are Monday-Friday, 5:00 a.m. – 7:00 p.m. Please contact us with any questions at HipStreets@cityofloveland.org or 970-962-2524.
Thank you for your continued patience and support.
Share Weekly project update 10/19 - 10/25/26 on Facebook
Share Weekly project update 10/19 - 10/25/26 on X (formerly Twitter)
Share Weekly project update 10/19 - 10/25/26 on Linkedin
Email Weekly project update 10/19 - 10/25/26 link